GM Service Manual Online
For 1990-2009 cars only

Starter Replacement RPO LS4

Removal Procedure


    Object Number: 1552773  Size: SH
  1. Disconnect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
  2. Remove the starter solenoid BAT terminal nut (3) and remove the positive battery cable (2) from the starter motor.
  3. Remove the engine harness terminal (4) from the starter motor.

  4. Object Number: 1552781  Size: SH
  5. Disconnect the starter motor electrical connector (1).
  6. Remove the air cleaner assembly. Refer to Air Cleaner Assembly Replacement .

  7. Object Number: 1552783  Size: SH
  8. Remove the starter motor bolts and starter motor.

Installation Procedure


    Object Number: 1552783  Size: SH
  1. Position the starter motor to the engine.
  2. Notice: Refer to Fastener Notice in the Preface section.

  3. Install the starter bolts.
  4. Tighten
    Tighten the bolts to 50 N·m (37 lb ft).


    Object Number: 1552781  Size: SH
  5. Connect the starter motor electrical connector (1).

  6. Object Number: 1552773  Size: SH
  7. Install the engine harness terminal (4) to the starter motor.
  8. Install the positive battery cable (2) and the starter solenoid BAT terminal nut (3) to the starter motor.
  9. Tighten
    Tighten the solenoid BAT terminal nut to 10 N·m (89 lb in).

  10. Install the air cleaner assembly. Refer to Air Cleaner Assembly Replacement .
  11. Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .

Starter Replacement RPOs LZE/LZ4/LZ9

Removal Procedure


    Object Number: 1617013  Size: SH
  1. Disconnect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
  2. Remove the front lower air deflector panel. Refer to Radiator Air Lower Baffle and Deflector Replacement .
  3. Remove the torque converter cover. Refer to Torque Converter Cover Replacement .
  4. Remove the starter solenoid BAT terminal nut (1) from the starter motor.
  5. Remove the positive battery cable terminal (2) and engine harness terminal (3) from the starter.

  6. Object Number: 1608498  Size: SH
  7. Disconnect the starter motor electrical connector (3).

  8. Object Number: 1617015  Size: SH
  9. Remove the starter bolts.
  10. Remove the starter.

Installation Procedure


    Object Number: 1617015  Size: SH
  1. Position the starter motor to the engine.
  2. Notice: Refer to Fastener Notice in the Preface section.

  3. Install the starter bolts.
  4. Tighten
    Tighten the bolts to 43 N·m (32 lb ft).


    Object Number: 1608498  Size: SH
  5. Connect the starter motor electrical connector (3).

  6. Object Number: 1617013  Size: SH
  7. Install the engine harness terminal (1) and positive battery cable terminal (2) to the starter. Ensure that the positive battery cable terminal anti-rotation feature is aligned correctly.
  8. Install the starter solenoid BAT terminal nut (3) to the starter motor.
  9. Tighten
    Tighten the nut to 10 N·m (89 lb in).

  10. Install the torque converter covers. Refer to Torque Converter Cover Replacement .
  11. Install the front lower air deflector panel. Refer to Radiator Air Lower Baffle and Deflector Replacement .
  12. Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .