Step | Action | Value(s) | Yes | No | ||||
---|---|---|---|---|---|---|---|---|
1 | Did you perform the RAP system check? | -- | Go to Step 2 | |||||
2 |
Is the voltage within the specified range? | 10-15 V | Go to Step 3 | Go to Step 4 | ||||
3 | Measure the voltage between the DAB ACSRY relay terminal C5 and ground. Is the voltage within the specified range? | 10-15 V | Go to Step 6 | Go to Step 7 | ||||
4 | Test CKT 1342 (RED) for an open or a short to ground. Is there an open or a short to ground? | -- | Go to Step 5 | |||||
5 | Repair the open or short to ground. Refer to Wiring Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
6 | Measure the voltage between the DAB ACSRY relay terminal B6 and ground. Is the voltage within the specified range? | 10-15 V | Go to Step 9 | Go to Step 10 | ||||
7 | Test CKT 40 (ORN) for an open or a short to ground. Is there an open or short to ground? | -- | Go to Step 8 | |||||
8 | Repair the open or short to ground in CKT 40. Refer to Wiring Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
9 |
Is the voltage within the specified range for approximately 10 minutes, and then open? | 10-15 V | Go to Step 15 | Go to Step 18 | ||||
10 | Test the following circuits for an open or a short to ground:
Is there an open or a short to ground in any of the CKTs? | -- | Go to Step 11 | Go to Step 12 | ||||
11 | Repair the open or short to ground in the faulty CKT. Refer to Wiring Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
12 | Ensure that the following C202 terminals are clean and tight:
Are the terminals clean and tight? | -- | Go to Step 14 | Go to Step 13 | ||||
13 | Repair the faulty terminals. Refer to Connector Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
14 | Replace the ignition switch. Is the repair complete? | -- | -- | |||||
15 | Ensure that the DAB ACSRY relay terminals are clean and tight. Are the terminals clean and tight? | -- | Go to Step 17 | Go to Step 16 | ||||
16 | Repair the faulty terminals. Refer to Connector Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
17 | Replace the DAB ACSRY relay. Is the repair complete? | -- | -- | |||||
18 |
Is the voltage within the specified range? | 10-15 V | Go to Step 19 | Go to Step 20 | ||||
19 | Measure the voltage between the RFA module connector terminal F15 and terminal F16. Is battery voltage present? | B+ | Go to Step 22 | Go to Step 23 | ||||
20 | Test CKT 143 (YEL) for an open or a short to ground. Is there an open or a short to ground in CKT 143? | -- | Go to Step 21 | |||||
21 | Repair the open or the short to ground in CKT 143. Refer to Wiring Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
22 | Measure the voltage between the RFA module connector terminal E16 and terminal F16. Is the voltage within the specified range? | 10-15 V | Go to Step 25 | Go to Step 26 | ||||
23 | Test CKT 1050 (BLK) for an open or a short to battery. Is there an open or a short to battery? | -- | Go to Step 24 | |||||
24 | Repair the open or short to battery in CKT 1050. Refer to Wiring Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
25 | Measure the voltage between the RFA module connector terminal E15 and terminal F16. Is the voltage within the specified range? | 10-15 V | Go to Step 28 | Go to Step 29 | ||||
26 | Test CKT 40 (ORN) for an open or short to ground. Is there an open or a short to ground? | -- | Go to Step 27 | |||||
27 | Repair the open or short to ground in CKT 40. Refer to Wiring Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
28 |
Is the resistance inifinite? | ∞ | Go to Step 31 | Go to Step 34 | ||||
29 | Test CKT 39 (PNK) for an open or a short to ground. Is there an open or a short to ground? | -- | Go to Step 30 | |||||
30 | Repair the open or short to ground in CKT 39. Refer to Wiring Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
31 | Ensure that the RFA terminals are clean and tight. Are the terminals clean and tight? | -- | Go to Step 33 | Go to Step 32 | ||||
32 | Repair the RFA terminals. Refer to Connector Repairs in Wiring Systems. Is the repair complete? | -- | -- | |||||
33 | Replace the RFA module. Is the repair complete? | -- | -- | |||||
34 | Test CKT 49 (DK BLU) and CKT 126 (TAN) and the door switches for a short to ground. Is there a short to ground? | -- | Go to Step 35 | |||||
35 | Repair Wiring Repairs in Wiring Systems. Is the repair complete? | -- | -- |