Step | Action | Value(s) | Yes | No |
---|---|---|---|---|
1 | Did you perform the Instrument Cluster Diagnostic System Check? | -- | Go to Step 2 | |
2 |
Is the voltage within the specified range? | 12-15 V | Go to Step 3 | Go to Step 6 |
3 | Test SBM connector C1 terminal contact. Is the terminal contact OK? | -- | Go to Step 5 | Go to Step 4 |
4 | Repair SBM connector C1 terminal contact. Is the repair complete? | -- | -- | |
5 | Replace the SBM. Is the repair complete? | -- | -- | |
6 | Test CKT 549 (PPL/WHT) for an open or short to ground. Is the circuit OK? | -- | Go to Step 8 | Go to Step 7 |
7 | Repair the open or short to ground in CKT 549 (PPL/WHT). Is the repair complete? | -- | -- | |
8 | Test the lamp control module (LCM) connector for proper terminal contact. Is the terminal contact OK? | -- | Go to Step 10 | Go to Step 9 |
9 | Repair the connector terminal contact. Is the repair complete? | -- | -- | |
10 | Replace the lamp control module. Is the replacement complete? | -- | -- |